Charging a 20-cart fleet: circuit sizing and charge windows

Update Date : 29.11.2026
Release Date : 29.11.2026
BY John

Add up the chargers, then halve it

A typical cart has a 1–1.5 kW onboard charger. Twenty carts charging simultaneously draw 20–30 kW, which is more than most depots have spare and far more than they need. Staggered charging across an eight-hour window cuts the peak to a third.

The number to design for is energy, not sockets: 20 carts × 5 kWh per day is 100 kWh, plus 20 percent for losses and partial-charge inefficiency. That is a 12–13 kW average load, comfortably inside a 32 A three-phase supply.

  • Energy per day = carts × kWh per cart × 1.2
  • Peak load = simultaneous chargers × charger rating
  • Schedule in three groups, two to three hours apart
  • Leave 20% headroom on the breaker for summer heat

Circuit and protection basics

Each charging point needs its own RCBO, not one breaker for the row. A single fault then takes out one cart instead of the depot, and nuisance tripping from a damp connector stays local. Cables should be sized for continuous duty, not for the short bursts a tool draws.

Outdoor points need IP-rated enclosures and a cable management hook. A connector lying in a puddle is the most common cause of a charger failure we see in the field, and it is entirely preventable.

Lead-acid and lithium want different habits

Flooded lead-acid prefers a full charge and does not like being left partial; it also vents hydrogen at the end of the cycle, so the charging area needs ventilation and no ignition source. Lithium is the opposite in daily use — it tolerates partial charging and should not sit at 100 percent for weeks.

For a mixed fleet, set the lead-acid carts to charge overnight to full, and the lithium carts to stop at about 80 percent unless a long route is planned the next day.

Temperature is the hidden variable

A pack at 40 °C charges more slowly and ages faster; a pack at 0 °C may refuse to charge at all until it warms. In hot climates, charge at night and shade the charging bay. In cold ones, charge immediately after use while the pack is still warm, and insulate the bay rather than the battery.

Chargers derate in heat as well. A 1.5 kW charger in a 45 °C shed may deliver 1.1 kW, which quietly turns an eight-hour window into eleven.

Commissioning checklist

Before the first season, walk the bay with an electrician and confirm four things: the design load, the protection per point, the ventilation, and the written charging rule that staff will actually follow.

  • Design load calculated from energy, not socket count
  • One RCBO per charging point, IP-rated outdoors
  • Ventilation for lead-acid; no ignition sources
  • Written schedule posted at the bay, not in a folder

What it costs to get wrong

An undersized supply trips at the busiest hour of the day, when every cart is back and every guest wants one. A charger without local protection fails and takes the row with it. And a fleet charged to 100 percent every night in a hot climate will replace packs a year early — the most expensive mistake in this list, and the easiest to avoid.

Contact Us

Professional manufacturer of electric four‑wheel vehicles
Whatsapp :

+86 189 5164 7014

Get an instant quote

Please fill out the form to send us message, we will get back to you within 2-3 hours on business hours.
Never spam. Thank you